NASA’s retained account establishes that Apollo 16 was delayed by one month in January 1972 and that a Command Module fuel tank damaged during a test required the Saturn V stack to roll back from the launch pad. It also records crew training, Duke’s hospitalization, and related Apollo 17 and Lunar Science Conference activities. What remains unproven is whether the retained page preserves exact original-day wording. [S1]

According to NASA, managers announced the delay on Jan. 7, moving the launch from March 17 to the next opportunity on April 16. NASA attributed the decision to incomplete spacesuit modification testing, needed testing of the Command Module docking ring jettison device, and additional data required to reverify the Lunar Module battery’s capacity. NASA said these activities were completed to meet the new launch date. [S1]

NASA said workers accidentally over pressurized a fuel tank in the Command Module’s reaction control system during a Jan. 25 test at Launch Pad 39A. The damage required a tank replacement that could not be performed at the pad, so the Saturn V rolled back on Jan. 27 to the Vehicle Assembly Building. NASA described this as the only rollback involving a flight vehicle, after an earlier June 1966 rollback for a test vehicle. [S1]

The account says workers removed the Launch Escape System tower, destacked the spacecraft, moved it to the Manned Spacecraft Operations Building, demated the Command Module from the Service Module, removed its heat shield, and replaced the damaged tank. Workers then reversed the process, reassembled the spacecraft, stacked it on the Saturn V, and rolled the vehicle back to the pad in two weeks to support the April 16 launch date. [S1]

NASA said Duke began feeling ill during a December 1971 geology field trip in Hawaii and was diagnosed with double bacterial pneumonia on Jan. 4, after which he was admitted to the Patrick Air Force Base hospital near Kennedy Space Center. The other crew members continued activities while he recovered for a week. NASA said doctors did not expect the illness to affect the original launch date, but the delay gave him additional time to resume training. [S1]

The account also describes crew training for the planned 12-day mission to the Descartes site in the Moon’s highlands. Mattingly and Roosa practiced a deep-space spacewalk to retrieve film cassettes from the Scientific Instrument Module bay, while Young, Duke, Haise, and Mitchell rehearsed lunar surface activities, including driving the Lunar Roving Vehicle. Young and Haise practiced descent and landing using the Lunar Landing Training Vehicle at Ellington Air Force Base. [S1]

NASA also reported leadership changes and related events. Administrator James C. Fletcher appointed Robert R. Gilruth to a new Key Personnel Development role and named Christopher C. Kraft as the center’s second director. Kraft then named Sigurd A. Sjoberg deputy director. The account also describes Apollo 17 geology training in Nevada and the third annual Lunar Science Conference, where more than 600 scientists from the U.S. and 13 other nations attended. [S1]

Source documents

  1. 50 Years Ago: Apollo 16 Delayed One Month, Rolls Back From the Launch Padhttps://www.nasa.gov/history/50-years-ago-apollo-16-delayed-one-month-rolls-back-from-the-launch-pad/

Source: retained text from NASA. Other pages were not independently consulted.