On July 23, 2019, the UK Cabinet Office issued Procurement Policy Note 04/19, replacing its 2018 predecessor and setting out how payment practices should be considered in major central-government procurement. Its rules were scheduled for relevant procurements advertised from September 1, 2019—not immediately on publication. [shared-bb88f9b7e8edd3bfa6fad1534e388ba09a727491d9218b0011221e4e34f18300]

The note covers central government departments, executive agencies and non-departmental public bodies. It applies to covered goods, services and works procurements subject to the Public Contracts Regulations 2015 when anticipated contract value exceeds £5 million per year, excluding VAT, unless exceptional circumstances make the approach irrelevant or disproportionate. The annual figure is based on advertised value averaged over the contract’s life. For framework agreements and dynamic purchasing systems, the test concerns the anticipated value of each individual contract. [shared-bb88f9b7e8edd3bfa6fad1534e388ba09a727491d9218b0011221e4e34f18300]

Where in scope, organisations were to add payment questions to section 6.2 of the standard selection questionnaire. Works procurement continues to use PAS91, with a project-specific question. The accompanying guidance describes assessing suppliers’ payment systems and circumstances in which exclusion may be appropriate; the note does not establish an automatic ban. The document does not specify a universal payment-days or percentage cutoff. It also does not cover every UK contract. The next evidence to watch is how contracting bodies implement the questions and apply the stated exceptions. [shared-bb88f9b7e8edd3bfa6fad1534e388ba09a727491d9218b0011221e4e34f18300]

Source documents

  1. Procurement Policy Note 04/19: Taking account of a supplier’s approach to payment in the procurement of major contractshttps://assets.publishing.service.gov.uk/media/5d36bc25e5274a400ce4c1b4/PPN_0419_FOR_PUBLICATION.pdf